A summary of the current status of our CP6 procurement process is outlined below, and a detailed indicative procurement programme is also available on our
supply chain webpage.
Prequalification phaseWestern and Wales recently held a supplier engagement event and were due to issue their prequalification questionnaire (PQQ) at the beginning of September. However, following further consideration and third party approaches around only inviting RISQ accredited suppliers, we have taken the decision to instead follow the OJEU procurement route.
Consequently, a PIN notice will be issued at the end of August and a further supplier engagement event will take place on the 21 September, with PQQ commencing in October 2018. ITT issue will be slightly delayed to February 2019, with contract awards planned for October 2019.
Prequalification for the £5bn Track alliances began this month, with ITT's issued in two stages - mid August and November, ahead of contract award in May 19.
The signalling work bank is being managed in three frameworks; Signal & Telecoms (S&T), Minor Signalling and Major Signalling. PQQs are due to be issued for S&T and minor signalling frameworks in early September, with ITTs expected to be issued in October.
Prequalification for the major signalling framework is set to begin in mid November, with the ITT following in January 2019, for contract award by early December next year.
Tender evaluation phaseThe tender evaluation period for Anglia, South East, Wessex, Scotland and London North East will commence this month, with contracts awarded by the end of the year.
This evaluation process is already underway for London North West and contract award is expected by mid-December.
As outlined above, the design services framework PQQ is scheduled for early October. With regards to the remaining professional services contracts; commercial services is due to issue a PQQ in September and the collaborative consultancy framework will award contracts at the end of October.
Our online
procurement pipeline will be updated each month to reflect the suppliers awarded each framework, should you wish to engage with them on the delivery of our projects.